(a) Draw the activity network described by the precedence table below, using activity on arc. Use dummies only where necessary.

ActivityImmediately preceding activities
A
B
CA
DA, B
EG, D
FD
GC
HG
IG
JE, H, I
KF, E

Given that K is a critical activity,

(b) state which other activities must also be critical.

(2)

Given instead that all activities shown in the precedence table have the same duration and K is not necessarily critical,

(c) state the critical path for the network.

(2)